Home Up Local Church Intercessions Thanksgivings Psalms
                                      

Home
Up
StrawBale Building
Straw2 Frame
Straw3 Roof
Straw4 Walls1
Staw 5 Walls2
Staw6 Stucco
Straw7 Stucco2
Straw8 Stucco3
Straw9 DryWall
Straw10 Doors

Why We Build

Building with Straw

We are extending the existing house by about 1600 feet. We are adding two more bedrooms, a bathroom and a multi-purpose great room where we can have gatherings and worship times. We got the building permit approved in October along with the electric lines and a new septic tank. The extension will be a post and beam construction with straw bale infill walls. We've seen several building like this and they are beautiful and very energy efficient homes to have in the desert southwest. (The 18 inch thick walls should keep our electric bill down quite a bit!)

The first thing we had to do was cut out a section of cement so that we could put our form right up against it. This was very slow and tedious work. By the end of the day, we renamed the process from "cement cutting" to cement filing".

We had to rip up the sod from our back yard and bring tons of dirt up to level it out.

 

Our electrician, Manny, lent us a frontloader/backhoe to help with the dirt work over the weekend. It was a huge help and saved us at least a couple weeks worth of wheel barrel work. Unfortunately there was one casualty from the backhoe. The freezer next to the foundation didn't make it. :(

Here is what it looked like after a week or so of working.

Since we had an existing sidewalk outside, we built a form right up to it. We eventually added some 2x4s on top of the sidewalk since the slab would be higher than the sidewalk.

A local Chaparral kid named Mike helped quite a bit on the foundation dirt work.

The entire roof weight will be supported by 15 4"x6"x16' posts planted around 5 feet in the ground and running up through the foundation. The final ceiling height will be around 10'.

We decided to run plastic under the entire slab for protection against moisture working up into our straw bales. The New Mexico straw bale code requires plastic to run up from the footing between the insulation up and over the edge of the foundation, then back. This is why we needed the extra plastic hanging over the edge. When the cement was dry, we'd pull it over the edge of the cement slab, then double it back for the straw to sit on. We weren't required to run it under the entire foundation, but we had heard it recommended as an extra deterrent to moisture.

Our plans required a 4" slab on a 12" wide x 18" deep footing. This meant that we would be wasting a lot of cement if we didn't get our dirt built up around the inner edge of the footing. Since the dirt was so loose and we hadn't packed it ahead of time, we had to build a moveable inner form to sure up the inside edge of the dirt before we put down the plastic. We couldn't get the nice inside edge without an inner form at this point. (Hind site told us we probably should have packed all the dirt into the outer form, then dug out the 12"x18" footing.) To work forward from where we were, we took two sets of 2"x12"x10's and held them together with 2 2"x4"s sticking down into the ground about 6 inches. Then we wedged a couple of pieces of extra 2"x4"s between the inner form and outer form for bracing. We filled in the extra dirt, packed it and wet it and then pulled away the form to do the next area. Since we had two 10' long forms, we could do 20' at a time. It took 3 of us about a day and a half to get it looking good, and we only had some minor amounts of dirt fall back into the trench. The cement guys estimated that we saved around $700 in cement by firming up the corners this way and not wasting any extra cement.

We weren't really sure what the best way was to tie in the posts to the foundation. We had bent the rebar around the corners then built boxes around posts with additional rebar. We then tied the boxes for each post into the rebar in the footing.

Since the posts were so deep, we only had to brace a few of them with 2x4s. As they poured the cement we just made sure they were still level.

We had a local team of cement guys do our cement pouring. We turned out using 33 yards of cement at around $59 a yard plus $900 in labor. Considering none of us had any tools or skills at cement pouring, this seemed like a great bargain.

After the cement began to dry, we put in rebar spikes about 18 inches apart. These will help the first layer of straw bales remain firmly locked into place. Here is what it looks like now that it is dry:

We'll soon be moving on to framing our addition and will have some updates as we move along.

If you are interested in helping or would like to see how we've put our plans together, or just want to hear how things are going, contact the .